PART II- TRANSPORT RELATED INFRASTRUCTURE REHABILITATION PROJECTS
TABLE 1- COMPLETED TRANSPORT REHABILITATION PROJECTS DURING 1993 -2003
Project Name |
Project Natural / Location |
Financial Sources |
Commencement and Completion Dates |
Roads: | |||
Rehabilitation of Bridges along RN5 & 6 | New construction of 11 bridges along RN 5 & 6 (RN 6-6 bridges: RN5 -5 bridges) |
Grant form Australia |
1993 1995 |
SRAL Project | Rehabilitate of some national roads and railway in Cambodian, and supply of equipment to Phnom Penh |
Soft Loan form ADB |
1993 1996 |
Rehabilitation of NR 6A, 44.5 km | Rehabilitate and upgrade RN6A from Phnom Penh to junction RN61 & RN6 |
Grant from Japan |
1994 1995 |
Rehabilitation of NR 4, 236km | Rehabilitate and upgrade RN4 from Phnom Penh to Sihanoukville |
Grant from USA |
1994 1995 |
Restoration of Chroy Chang Wa Bridge | Rehabilitate Chroy Chang Wa bridge which was destroyed during civil war |
Grant from Japan |
1994 1995 |
Odem Heavy Equipment Center Project | Build new workshop and supply of 4 heavy equipment brigades |
Grant from Japan |
1994 1996 |
Rehabilitation of NR6 & 7 km, 74.5km | Rehabilitate and upgrade RN6 and 7 from end of RN6A to Kompongcham |
Grant from Japan |
1997 1999 |
New Mekong Bridge Construction, Kizuna Bridge | New bridge construction across Mekong river at Kompongcham province along NR7 |
Grant from Japan |
1998 2001 |
Rehabilitation of NR7, 12km | Rehabilitate and upgrade RN7 from to Kizuna bridge to junction RN7 & RN11 |
Grant from Japan |
2000 2003 |
Bridge Restoration Project along RN6A | Reconstruct three bridges (Bridges No. 24, 25 & 26) along RN6A |
Grant from Japan |
2000 2003 |
Rehabilitation of RN6, 17.5km | Rehabilitation and upgrade RN6 from Siem Reap to Prey Rolous |
Grant from Japan |
2000 - 2002 |
Rehabilitation of RN5, 91 km | Rehabilitation and upgrade RN5 from Phnom Penh to Kompongchhnang |
National Budget |
2000 2002 |
ADB Loan 1824-CAM (SF):Flood Emergency Relief Project, Part A, Transport Sector, 449 km |
Rehabilitation of RN damaged by the floods of 2000 and 2002: |
Soft Loan from ADB |
2000 2004 |
Port: | |||
Phnom Penh Prot Project | Build new terminal berth and supply of equipment |
Grant from Japan |
1994 1996 |
Phnom Penh Floating Port | Build new 2 floating ports and supply of equipment |
Load from World Bank |
1995 - 1997 |
TABLE 2- ON-GOING TRANSPORT REFIABILITATION PROJECTS
Project Name |
Project Nature / Location |
Costs |
Financial Sources |
Commencement and Completion Dates |
Roads: | ||||
ADB Loan 1697-CAM (SF) Primary Roads Restoration Project, 405 km |
Rehabilitate and upgrade RN 5, 6 & 7: RN5: from Krakor to Battombang, RN6: from Kompongthom to Prey Romeas |
US$ 88 mil. |
Soft Loan from ADB OPEC, Australia |
2000 - 2005 |
ADB Loan No. 1659-CAM (SF): Phnom Penh- Ho Chi Minh Highway Project, 105 km | Rehabilitate and upgrade RN 1 from Nak Loeng to Cambodia-Viet Nam Boarder |
US$32 mil. |
Soft Loan from ADB |
1999- June 2005 |
Emergency Flood Rehabilitation Project, 270.5 km | Rehabilitate RN3, RN33, RN31 & RN61 |
US$ 12 mil. |
Soft Loan from World Bank |
2000-2004 |
Credit No. 3181 -KH Road Rehabilitation Project, 140 km |
Rehabilitate and upgrade RN6, RN3, RN51, Phnom Penh & Siem Reap Municipal Roads |
US$ 42 mil. |
Soft Loan from World Bank |
2000-2004 |
ADB Loan 1945-CAM (SF): Cambodia Road Improvement Project |
Rehabilitate and upgrade RN 5 & 6 from Poi Pet Siem Reap, 150 km; and Structure on RN 56 and 68 |
US$ 87.5 mil. |
Soft Loan from ADB & OPEC |
2004 -2007 |
Rehabilitation Project of National Road No. 7 |
Rehabilitate and upgrade RN 7 from Kratie to Cambodia - Lao Boarder, 196 km |
520 mil Yon |
Soft Loan from People Republic of China |
2004 - 2008 |
Kompot- Trapangropeou Road Rehabilitation Project | Rehabilitate and upgrade RN 3 from Kompot Town to Trapangropeou, 32.5 km |
US$ 19 mil |
Soft Loan from South Korea |
2004-May 2007 |
Koh Kong Sre Ambel Road Improvement Project | Rehabilitate and upgrade RN 48 from Koh Kong to RN4, 152 km |
867.8 mi Bath |
Soft Loan from Thailand |
2004 -2006 |
Provincial and Rural Infrastructure Project | Rehabilitate and upgrade selected national roads in 4 northern provinces of Cambodia, Siem Reap, Kompongthom, Odormeanchey and Pravihear app . 800 km |
US$ 20 mil (US$ 12 mil. MPWT; US$ 8 mi. MRD) |
Soil Loan from World Bank |
2004 2008 |
Road Rehabilitation RN2 Orchambok - Cambodia/ VN boarder | Rehabilitate and upgrade RN2 from Takeo town to Cambodia-Vietnam Boarder |
US$ 12.4 mil |
Japan Counterpart Fund |
2003 2005 |
Port: | ||||
1st Emergency Rehabilitation Project of Sihanoukville Port | Build 240m- container terminal berth, stacking yard, inspection building, water supply & fence, and supply of generator set |
JPY 4,142 mil. (US$ 39,4 mil.) |
JBIC Soft Loan No. CP-P3 |
2003 March 2005 |
Railway: | ||||
Supply Project of rail stock & locomotives | Supply of rail stock & locomotives |
US$ 13 mil |
National Budget |
2003 2005 |
TABLE 3 TRANSPORT REHABILITATION PROJECTS IN PIPE LINE
Project Name |
Estimation Cost |
Expected Financial Sources |
Expected Commencement and Completion Dates |
Remarks |
Road: | ||||
Rehabilitation Project of RN 68 from RN6 (Kralanh) to Cambodia - Thai border, 117 km excluding structure |
US$ 26 mil |
Soft Loan from Thailand |
2006 2008 |
Letter of request for soft loan was sent to Royal Thai Government in November 2004 |
Rehabilitation Project of National Road No. 67 from Siem Reap Town to Cambodia Thai border, 132 km |
US$ 45 mil |
Soft loan from Thailand |
2005 2007 |
100 mil. Bath was granted for the on-going project study; and load is expected in 2005 |
Kompot- Phnom Penh NR3 Rehabilitation Extension Project, 148 km |
US$ 60 mil |
Soft Loan from South Korea |
2006 - 2008 |
Letter of request for loan was sent to South Korean Government in November 2004 |
Project of Four Bridges Along RN 48 |
300 mil Bath (US$ 7.5 mil.) |
Grant from Thailand |
2005 - 2007 |
Civil Work Bidding is in Process |
Three Bridges at Kondal Province, Takhmao |
JPY 848.2 mil US$ (7.75 mil.) |
Grant from Japan |
19 months |
|
Rehabilitation Project of NR 1 from Phnom Penh to Nak Leung includes 2nd National Mekong bridge, 61 km and asphalt concrete overlay o(NR6A & 7 from Phnom Penh to Kompongcham Town, 124 km |
(US$ 170 mil.) |
Grant from Japan |
2006-2008 |
Study completed; Constrain is resettlement |
RN78 Road Rehabilitation Project |
US$ 25 mil. |
Loan from Vietnam |
2005-2008 |
Detail Design Study is in progress |
Port: | ||||
2nd Phase of Sihanoukville Port Extension Project to extend container terminal berth and equipment supply |
JPY 4,313 mil (US$ 40 mil) |
Soft Loan from JBIC |
2005-2007 |
Loan signing end of November 2004 |
Railway: | ||||
Rehabilitations of Missing Link between Poi Pet and Sisophon, 48km |
US$ 22 mil |
Soft Loan from Malaysia |
2006 2007 |
Malaysia Government donate 106km of used rail tracks To be confirmed by Malaysia |
TABLE 4 TRANSPORT REHABILITATION PROJECTS PLANED FOR THE YEAR 2006 - 2010
Project Name |
Estimation Cost |
Expected Financial Sources |
Expected Commencement and Completion Dates |
Remarks |
Road: | ||||
Rehabilitation of RN 57 from Battombang to Cambodia Thai border, 94 km |
US$ 38 mil. |
Grant from Japan |
2007 2010 |
To be confirmed by Japan |
Rehabilitation of RN33, RN72 and RN56, 130km |
US$ 40 mil |
Soft Loan from ADB |
2006 2009 |
To be confirmed by ADB |
Rehabilitation of RN 66 from Siem Reap to Stung Treng include 3rd Mekong bridge ant Stung Treng, 200 km |
US$ 110 mil |
Soft Loan from ADB |
2007 - 2010 |
To be confirmed by ADB |
Rehabilitation of RN 76 from Snoul to Mondulkiri and Ratanakiri, 305 km |
US$ 92 mil |
Soft Loan from ADB |
2007 2010 |
To be confirmed by ADB |
Port: | ||||
New Construction of 300m-Berth for Bulk Cargo and Supply of Berth Associated Equipment |
US$ 36 mil |
BOT Project is acceptable |
2006 2010 |
The project include also stacking yard of app. 12 hectare |
New Construction of 265m-Berth for General Cargo and Dredging of Approach Channel |
US$ 10 mil |
Sihanoukville Port Authority |
2006 2008 |
The project also includes quay apron of 8,000 sp.m |
Sihanoukville Free Industrial Zone Project |
US$ 28 mil |
Sihanoukville Port Authority |
2005 2008 |
Feasibility Study completed by JICA Project will provide jobs to 10,000 employees |
Upgrade Phnom Penh Dry Port Project |
US$ 1.5 mil |
Sihanoukville Port Authority |
2006 -2010 |
The project includes build new railway access to Phnom Penh Dray Prot, strengthening management capacity and environment mitigations |
Rehabilitation of Existing Cargo Berth |
US$ 1.0 mil |
Sihanoukville Port Authority |
2007 2008 |
The existing cargo berth will be rehabilitated and modified to passenger berth |
Environmental and Anti-terrorist Protection Project |
US$ 5.0 mil |
Sihanoukville Port Authority |
2005 2006 |
The project also includes strengthening port authority with oil spilt protection program |
Sihanoukville Wind Power Project |
US$ 1.0 mil |
Sihanoukville Port Authority |
2005 2006 |
Supply of environmentally friendly energy to Sihanoukville Port Authority |
Procurement Project of Phnom Penh Prot Fixed Crane |
US$ 3.0 mil |
Seeking |
2005 |
Two fixed crane are required to cope with the increase of container cargo and to improve efficient operation |
Phnom Penh Inland Container Depot Development Project |
US$ 7.0 mil |
Seeking |
2005 2007 |
Existing Phnom Penh Port site at PK 5 need an upgrading and development to cope with cargo increase |
Phnom Penh Inland Container Depot Development Project |
US$ 5.0 mil |
Seeking |
2005 2007 |
Phnom Penh Inland Container Depot Development sites of 3 locations at Takhmao along Bassac River, Prek Anhchanh, at Kampongcham along Mekong River are required to cope with cargo increase |
Dredging river bed along the Mekong River |
US$ 4.5 mil |
Seeking |
2004 2007 |
|
Dredging River bed along Tonle Sap River |
US$ 21 mil |
Seeking |
2004 2007 |
|
Supply of two harbor tugboats with capacity of 550 hp |
US$ 1.5 mil |
Japan Grant |
2004 2007 |
|
Rehabilitation of River Port |
US$ 6 mil |
Japan Grant |
2005 2007 |
|
Railway: | ||||
Rehabilitation of Railway between Sisophon-Phnom Penh, 338km |
US$ 40 mil |
ADB |
2006 2009 |
|
Rehabilitation of Railway between Phnom Penh-Sihanoukville town 264 km |
US$53 mil |
Seeking |
2006 2007 |
|
Construction of new railway link between Phnom Penh (Bat Deung) and Loc Ninh (Viet Nam) |
Us$ 500 mil |
Seeking |
- |
Feasibility Study on Tran-Asia Road and Rail Project completed by Malaysian Transport Ministry |
TABLE 5 TECHNICAL ASSISTANCE PROJECTS IN PIPE LINE
Project Name |
Estimation Cost |
Expected Financial Sources |
Expected Commencement and Completion Dates |
Remarks |
Adoption of Cambodia Road Standard Project |
US$ 0.15 mil |
Grant from ADB |
2005 |
To be confirmed by ADB |
National Road Master Plan Project |
- |
Grant from Japan |
2005 2007 |
Project Preparatory Study completed in November 2004 |
Regional PPTA for RN 33 |
US$ 1.2 mil (Cambodia & Vietnam) |
Grant from ADB |
2005 |
To be confirmed by ADB |
Railway Master Plan |
US$ 0.5 mil |
Seeking |
2005 |
|
Project Preparation Study of RN 78 from VB-Cambodia border to Rattanakiri and from Rattanakiri to Stung Treng, 189 km |
- |
Grant from Vietnam |
2005 |
Technical Study is in process |
TABLE 6 TECHNICAL ASSISTANCE PROJECTS PLANED FOR THE YEAR 2006-2010
Project Name |
Estimation Cost |
Expected Financial Sources |
Expected Commencement and Completion Dates |
Remarks |
Master Plan for Waterborne Transport on the Mekong River System |
Euro 0.75 mil |
Belgium Govt |
2005 2006 |
To be confirmed by Belgium Govt |
Waterway Management Transport and Navigation Safety Implementation Program |
US$ 0.15 mil |
Grant from ADB |
2005 2006 |
To be confirmed by ADB |
Finalization of Road Law (Acts) & Road Safety Program & HR |
US$ 0.5 mil |
Grant from WB |
2005 2006 |
To be confirmed by WB |
TABLE 7 IMPLEMENTATION PROGRAMS FOR LAND, MARITIME AND WATERWAY TRANSPORT
Project Name |
Estimation Cost |
Expected Financial Sources |
Expected Commencement and Completion Dates |
Remarks |
Land Transport: |
US$ 37.4 mil |
Seeking |
2004 - 2008 |
|
Maritime Transport:
|
US$ 7.3 mil |
Seeking |
2005 2008 |
|
Waterway Transport:
|
US$ 1.2 mil |
Seeking |
2004 - 2008 |
TABLE 8: ROAD MAINTENANCE
Description |
Funding USD |
Years |
Sources |
Remarks |
Maintenance of 4,189 km of National and Provincial Rehabilitated Roads (literate roads) |
86 mil |
2004 2008 |
Seeking |
|
Routine Maintenance of 2,500 km of National and Provincial Roads (bituminous road) |
60 mil |
2004 2007 |
Seeking |
|
Maintenance of National Roads: RN6, RN8 and RN 53 |
23 mil |
2004 2008 |
Seeking |
TABLE 9: SUMMARY OF COSTS
Description |
Budget / US$ Million |
Remarks |
Committed |
492.3 |
On-going Transport Rehabilitation Projects |
Non-committed |
739 |
(1) |
Seeking |
845 |
(2) |
Total Budget for the year 2006 2010 |
1,584 |
(1+2) |