4.    GOVERNMENT’S  POLICY PERFORMANCE

39.    In the history of CG Meetings for Cambodia that have been held so far, it was for the first time in late 2004 that the Royal Government and the development partners have had an opportunity to jointly review and agree on a set of monitoring indicators to review progress. These discussions were held at the first meeting of the newly created high level Government-Donors Coordination Committee (GDCC) a few days before the 7th   CG Meeting. Since the 7th CG meeting, the GDCC has met quarterly to review progress on the Joint Monitoring Indicators (JMIs) that were agreed upon at the 7th CG meeting held on 6-7 December 2004. These quarterly reviews by representatives of the Royal Government and development partners -- who have included Senior Ministers, Ministers or


Policy Performance
 

4.1    Fighting Corruption and Increasing
        Accountability
4.2    Legal and Judicial Reform and Protection
        of Human Rights
4.3   Public Administration Reform
4.4   Decentralization and De-concentration
4.5   Public Financial Management
4.6   Cross-cutting for Agriculture and Natural
       Resources Management
4.7   Private Sector Development
4.8   Gender, Poverty and HIV/AIDS
4.9   Health and Education
4.10   Harmonization and Alignment

 heads of government agencies, Ambassadors or heads of diplomatic missions, and heads of multilateral institutions -- have provided an opportunity to both sides to regularly review progress and be informed about constraints that are being experienced, and enabled them to take necessary actions.
 
40.   The 18 sector/thematic Joint (Government-Donor) Technical Working Groups and the high level GDCC mechanism that became operational following the last CG meeting has begun to have an impact on moving forward the RGC reform programs. The quarterly reviews of progress at the high level GDCC meetings have kept focus of ministries and agencies as well as development partners on achieving the targets of the agreed JMIs throughout the year. This mechanism has also enabled both sides to appreciate the constraints that are being faced and has provided an opportunity to take appropriate actions.  The year 2005 has been a year of learning-by-doing for both ministries/agencies as well as development partners. On both sides, as in any endeavor, some have rapidly moved on to make the new mechanism work while others are following.
 
41.       Overall, significant progress has been made in achieving the targets of the Joint Monitoring Indicators (JMIs) that were agreed at the last CG meeting. One issue that has emerged is the lack of correlation between activities that were needed to be carried out to achieve the targets of the JMIs and the resources mobilized to carry out these activities. The periodic reviews of progress during 2005 have revealed that significant progress was being made in areas where a clear linkage between planned activities and the resources needed to implement the activities had been established; as compared to areas where this linkage was either weak or missing, or there was a lack of ownership by concerned institutions. 
 
42.    At the Fifth GDCC Meeting held on 12 December 2005, on behalf of the Royal Government, the Chair of GDCC asked development partners to make effective use of the TWG mechanism for identifying the JMIs for endorsement at the next CG meeting. Based on the principle of mutual accountability, the Royal Government would like the TWGs to not only identify the JMIs to monitor progress of their work -- in an environment where the Government side takes ownership of the process and most of the responsibility -- but also to (i) identify who will be responsible for the work needed to achieve the targets of each proposed JMI; and (ii) the resources required to carry out the work as well as identify donors who will provide the needed resources. The Royal Government would like to see TWGs setting realistic time frames for achieving the targets by taking into account the existing capacity of the concerned institutions for carrying out the required tasks and the complexities of the processes involved.
 
43.    In terms of progress in achieving the targets of the JMIs agreed at the 7th CG meeting held on 6-7 December 2004, the progress made in each area is summarized below. 

4.1    Fighting Corruption and Increasing Accountability

44.    At the 7th CG Meeting, the following JMIs were agreed to in this area:

  1. Within the existing criminal law, reported cases of corruption shall be brought before the courts for investigation and hearing; a consistent and strategic approach shall be employed by law enforcement authorities to the prosecution of cases of corruption. Data shall be collected to enable monitoring of progress.

  2. The existing draft law on anti-corruption shall be brought into compliance with international best practice [such as reflected in the United Nations Convention against Corruption or other instruments].

  3. The Government should commence preparatory work on establishing a legislative framework (such as a Freedom of Information Law) to facilitate access to information held by public authorities.  In the meantime, public authorities must change current practice by displaying a preparedness to share information with the general public and with other institutions in Government.  The different TWGs will monitor specific indicators of access to information.

45.   Significant progress has been made in 2005 in moving forward to deal with the three JMIs in this area. With respect to the first JMI, the Ministry of National Assembly-Senate Relations and Inspection (MoNASRI) was mandated by Samdech Prime Minister to report on cases of corruption. MoNASRI has provided detailed reports at the GDCC meetings on high profile cases such as the missing food-for-work case and case of corruption involving judges, prosecutors and court clerks.

46.   After extensive consultations and revisions based on inputs from various parties, the Ministry of National Assembly-Senate Relations and Inspection (MoNASRI) that is responsible for overseeing the drafting of the Anti-corruption Law submitted a draft to the Council of Ministers. The consultation process in 2005 has included:

  • The formation of a Sub-working Group of the Legal and Judicial Reform TWG that was chaired by the Chairman of the Anti-corruption Law drafting Committee. Its members have included, in addition to government officials, representatives of development partners and two NGOs -- the Centre for Social Development and Cambodian Defenders Project. A number of international experts have been involved in the drafting process.

  • Based on the inputs a revised draft was prepared. It was presented at a two-day workshop held on 17-18 August 2005 in Phnom Penh in which all stakeholders participated. The workshop was opened by Samdech Prime Minister.

  • Following this workshop, after further revisions by MONSARI, the draft was submitted to the Council of Jurists on 12 December 2005. After approval by the Council of Jurists it will be submitted to the Council of Ministers for review and approval.

  • The approved Anti-corruption Law incorporates the essential principles of the United Nations Convention against Corruption and other relevant instruments.

47.    On the third JMI in this area, a number of concrete actions have been taken in 2005 to increase access to information held by public authorities. For example:

  • The Department of Fisheries has opened the bidding process for fishing lots to the public.

  • MAFF has begun to release information on economic land concessions. The first batch of information that included names of concession companies which have signed an agreement or are in the process to finalize an agreement with MAFF has published. Additional information providing details on land concessions will be posted on MAFF website in the second quarter of 2006.

  • Information on forest concession reviews is now available at Public Affairs Unit of the Forestry Administration.

4.2    Legal and Judicial Reform and Protection of Human Rights

48.    At the 7th CG Meeting, the following JMIs were agreed to in this area:

Fundamental Legal Framework: Adoption of the drafts of the 8 fundamental laws by the Council of Ministers and submission to the National Assembly as a matter of urgency:

  1. Penal Code

  2. Code of Penal Procedures

  3. Civil Code

  4. Code of Civil Procedures

  5. Organic Law on the Organization and Functioning of Courts

  6. Law on the Amendment of the Supreme Council of Magistrates (reflecting transparency in appointment, promotion, transfer, remuneration and disciplining of judges and prosecutors, and ensuring the independence of Judges and Prosecutors) - rolled over

  7. Law on the Status of Judges and Prosecutors - rolled over

  8. Law on Anti-Corruption - rolled over

49.   Significant progress has been made in drafting the Laws in 2005. A total of 45 Laws were approved by the National Assembly in 2005, as compared to a total of 90 Laws over five years from 1993 to 1998. In addition, other Laws have also been submitted to the National Assembly during 2005 that have not yet been approved by the National Assembly. The Royal Government would like to urge all parties to be realistic in setting time frames for the completion of work on the drafting of these Laws taking into consideration the existing capacities of concerned institutions and available resources as well as the complexities of the processes in securing approval of proposed draft Laws at the various levels of the Executive and Legislative branches. The current status on the preparation of these Laws is as follows:

  • Penal Procedures Code is being reviewed by the Inter-Ministerial Meeting and is expected (at the date of preparation of this report) to be finalized by the end February 2006.

  • Penal Code has been revised by the Council of Jurists and will be scheduled to be reviewed by the Inter-Ministerial Meeting.

  • Civil Code is being reviewed by the Inter-Ministerial Meeting.

  • Code of Civil Procedures has been reviewed by the Permanent Committee of National Assembly and will be scheduled for debate at the full session of the National Assembly.

  • Organic Law on the organization and Functioning of the Courts has been reviewed by the working group of the Ministry of Justice.

  • Law on the Amendment of the SCM has been drafted and reviewed by the Council of Jurists. The working group of the Ministry of Justice is working to refine the draft.

  • Law on the Statutes of Judges and Prosecutors has been drafted and reviewed by Council of Jurists. Now the working group of the Ministry of Justice is working to refine the draft.

  • Progress on the Anti-corruption Law is reported in the preceding section.

4.3    Public Administration Reform

50.     At the 7th CG Meeting, the following JMIs were agreed to in this area:

  1. Agreement between government and donors on a strategy to phase out donor-funded salary supplements and redirect them in support of pay reforms in priority areas by June 2005. (Ref. to RGC’s Action Plan for Harmonization and Alignment, Section D.1.c and NPAR priorities section 2.1.3)

  2. The Council of Ministers approve by November 2005 for implementation starting in January 2007, a phased medium-term civil service remuneration plan to improve civil service pay selectively to appropriate levels, that will allow the public administration to attract and retain talent. The plan shall be coherent among State institutions, sustainable and consistent with the RGC approved Medium-term Expenditure Framework. (Ref. to NPAR priorities section 2.1.1, 2.1.3 and 5.1 and PFM Consolidated Action Plan measures 2.3 and 2.4).

  3. Pilot implementation of pay and employment reform initiatives--that are fully consistent with each other-- and that reward performance and promote merit in at least 3 sectors or professional streams during 2006

  4. Gradual reduction of cash transactions in the payment of salaries through the use of the banking system and electronic transfers. Parameters and preparation of pilots for payments via electronic bank transfers completed by November 2005 (Ref. to NPAR priorities section 2.1.2 and PFM Consolidated Action Plan 7.12).

  5. A meritocratic human resource policy with a detailed and sequenced implementation plan will be adopted by the Council of Ministers.

51.    Significant progress has been made in 2005 in moving forward to deal with the five JMIs in this area. With respect to the first JMI, after extensive consultation, the strategy has been finalized and was agreed to by the TWG at a meeting on 26 January 2006. Implementation commenced on 27 January with the information questionnaire being sent to donors, for response by 28 February 2006. The core of the strategy relies on the implementation of PMGs and PMG/MBPIs at the sector level and making supplementation practices more transparent and harmonized.

52.     With respect to the second JMI, a new remuneration regime more conducive to performance has been in operation since 2002. Pay reforms must be sustainable and depend essentially on government revenues. The Royal Government's approach has been to target priority functions (management, education, health) and priority missions while increasing base salary as much as possible. Average remuneration has increased by 116% since January 2002. Further allowances will be introduced shortly to enhance mobility and compensate for risks. Ways and means to accelerate the pace are being investigated with three studies on remuneration, employment and the labor market to be completed in time to inform decision making on a medium strategy in June 2006.

53.    On the third JMI, progress has gone beyond piloting the Sub-Decree 98, it is now authorized to be implemented across the Administration. PMG and PMG/MBPI are being implemented on a wide front. A first PMG/MBPI is operational to support the PFM. Others are being developed to support reform programs in land, health, commerce and others. More than 10 ministries and agencies are actively involved.

54.    With respect to the fourth JMI, the activity under this indicator is being managed in the Ministry of Economy and Finance where good progress is being made.

55.   On the last JMI in this area, core HR processes are being strengthened in support of performance and merit. A detailed HRM guide is in the final stage of preparation. Building on the outcome of a national seminar, a HRD Master Plan is being developed. Related HRM and HRD policies are scheduled for discussion by the PAR TWG in March. Effective mechanisms are in place to control the establishment.

4.4    Decentralization and De-concentration

56.    At the 7th CG Meeting, the following JMIs were agreed in this area:

  1. The RGC National Policies, Strategic Framework, Action Plan finalized by March 2005 and submitted to Council of Ministers for approval.

  2. The first draft prepared for consultation of the D&D organic Laws on the Management of Provincial & District, Municipalities and the Capital, produced within the D&D strategic framework.

57.   In 2005, substantial and encouraging progress was made on decentralization and de-concentration reforms, in particular on the two agreed JMIs.

58.    As regards the first JMI, a draft of the RGC’s Strategic Framework for D&D was prepared, reviewed at the highest levels of the RGC, and discussed at a national workshop opened by Samdech Prime Minister   and co-chaired by the two Deputy Prime Ministers and Co-Ministers of the Ministry of Interior. The Strategic Framework was later revised and adopted by the Council of Ministers on 17 June 2005.

59.     The Strategic Framework sets the policy and principles for restructuring and reformation of all levels of sub-national administration (provinces, municipalities, districts, khans, communes, and sangkats) and corresponding adjustments to the national administration. The essential purpose is to establish and promote democratic development at the sub national levels through decentralization and de-concentration,  and the better delivery of programs, services and infrastructure. 

60.     With respect to the second JMI, the drafting of the Organic Laws was started in 2005.  The first drafts will be completed by the end of the first quarter of 2006 and will be discussed with stakeholders, including the TWGD&D that was established on 25 November 2005.

61.    Another encouraging development on D&D, initiated by the Ministry of Interior through the IMC Task Force, was the commissioning in September 2005 of an Independent Study to undertake a comparative review of donor funding support and services for decentralization and de-concentration, including all funding programs; institutional arrangements for funding; funding mechanisms; and Seila.

62.    The study, which will be completed by the end of the first quarter of 2006 in consultation with development partners, is expected to provide essential inputs for improving cooperation, understanding and consultation between the Government and the donor community on the methods, modalities and mechanisms for ensuring optimum long-term donor support for democratic development at sub-national level.

4.5    Public Financial Management

63.    At the 7th CG Meeting, the following JMI was agreed to in this area:

  • Implement RGC's PFM reform agenda: first 12 months of platform 1.

64.   The Public Financial Management Reform Program (PFMRP) is being successfully implemented to complete the activities planned for the first 12 months of platform one. Although this comprehensive and long term PFMRP is still at an early stage of the implementation, progress over the first year has been satisfactory and significant impact is being noted on both revenue and expenditure sides. Specifically, substantial progress has been made in several areas such as change management (especially in institutional change and ownership and responsibility building), capacity development, macro-fiscal forecast and management, budget formulation and execution, procurement procedures, internal audit, cash management, and a significant improvement in both tax and non-tax revenue collection.

65.    The PFMRP consists of 27 activities which break down into 254 actions that were planned to be implemented in stage one. Out of the 254 actions, 224 actions were planned to be carried out in 2005 of which 208 (93%) activities were implemented as scheduled and the implementation of 16 (7%) actions was delayed. Of the total planned activities, work on 35 (16%) of the planned activities was completed in 2005, while implementation of 173 (77%) activities was on-going at the end of 2005. Of these on-going activities, progress on 25 activities was judged to be below expectations. The delays in implementation and slow progress in some actions/areas were mainly due to several reasons such as inappropriate sequencing of actions, cross-cutting actions/activities, additional analysis and/or consultation requirement, additional technical assistance need, better cooperation and coordination and pro-active of all key players/stakeholders requirement.

66.    Due to the comprehensiveness and complexity, the program is managed and monitored based on a management framework and a set of performance measurement indicators which monitor and review monthly, quarterly and annually. Under the umbrella of Public Financial Management Technical Working Group (PFMTWG), a Reform Committee (RC) has been established to lead and coordinate on the Government side as well as a Development Partner Committee has also been established to lead and coordinate on the development partners side. The RC and DPC meet monthly and the PFMTWG meets quarterly. Currently the program is subject to be reviewed two times a year (mid-year and annual) by the PFMTWG and through an external independent evaluation. The first annual review of the program is being carried out to assess progress and challenges, to review action plan and performance measurement indicators, to review the first phase implementation of Merit Based Pay Initiative (MBPI), and finally to agree on the revised action plan and performance measurement indicators and the second phase of MBPI implementation which is scheduled to be completed in late March 2006.

4.6    Cross-cutting for Agriculture and Natural Resources Management

67.    At the 7th CG Meeting, the following JMIs were agreed in this area:

  1. Pass/enact key laws and sub decrees, governing natural resources management, including fisheries law and community fisheries sub decree (rollover), state land management and economic land concessions sub decrees and enforcement of Article 18 of Land Law, that private sales transactions on state lands are illegal and hence should not be validated by officials.  Joint development of a medium term sector strategy for agriculture, including irrigated agriculture, has been commenced by March 2005, with an overall policy and strategic framework completed by December 2005.

  2. Maintain suspension/moratorium on logging, transport of logs (except those which have been already inventoried and for which royalties have been paid in full), and new economic land concessions pending completion of applicable review processes and/or a legal framework.

  3. Increase transparency of state management of natural resources through immediate public disclosure of existing contracts and compliance status (royalties and other key provisions) of contracts governing economic land concessions, mining concessions, fishing lots and continued disclosure of status of review of forest concessions.

  4. Application of sustainable management planning, including ESIAs, investor evaluations, consultation with local communities, public disclosure and comment period prior to entering into new contracts for private use/management of state managed natural resources (land, fisheries, forestry, and mines).

  5. RGC disclose the location and legal status and process for termination of mining concessions, Military Development Zones, economic land concession and other development arrangements situated on forest land or in protected areas and inconsistent with law governing management of these areas. 

68.    Significant progress has been made on all JMIs in this area since the last CG meeting. The TWGs in this area have played an important role in moving forward the reforms and have tried to follow the principle of mutual accountability in their work.

69.    With respect to the first JMI is this area, the:

  • Statement of the Royal Government on National Fisheries Sector Policy was issued on 15 June 2005.

  • Draft Fisheries Law was prepared and sent to the National Assembly.

  • The Royal Decree on Community Fisheries was signed by His Majesty the King on 29 May 2005. The Sub-Decree was signed by Samdech Prime Minister on 10 June 2005. The Department of Fisheries conducted a meeting in July 2005 with NGOs and provincial fisheries offices to disseminate information on the Royal Decree and the Sub-Decree.

  • Provincial fisheries offices have been disseminating information on the Royal Decree and the Sub-Decree at the community levels.

  • Sub-Decree on SLM was approved and implementation is in progress. The Sub-Decree on ELC is being considered by the Council of Ministers. Discussions on enforcement of Article 18 of the Land Law are on-going.

70.    On the second JMI in this area concerning the moratorium on logging and transport of logs, the TWG on Forestry and Environment has reported to GDCC that the targets of this JMI have been met. It has also raised a concern that available wood supply might not meet the increasing domestic demand due to logging moratorium.

71.    The third JMI in this area concerning the transparency of state management of natural resources, the TWG on Forestry and Environment has reported to GDCC that the targets of this JMI have been met. It has reported that:

  • Information on forest concession reviews is now available at Public Affairs Unit of the Forestry Administration.

  • The Department of Fisheries has opened the bidding process for fishing lots to the public.

  • MAFF has begun to release information on economic land concessions in accordance with Samdech Prime Minister's notice following 30 June with development partners. The first batch of information that included names of concession companies which have signed an agreement or are in the process to finalize an agreement with MAFF has been published. Additional information providing details on land concessions will be posted on MAFF website in the second quarter of 2006.

72.    The fourth JMI in this area concerning the application of sustainable management planning, the TWG on Forestry and Environment has reported to GDCC that the targets of this JMI have been met. It has reported that:

  • SFMPs of forest concession plans are being reviewed according to procedures set under the sub-decree.

  • Department of Fisheries in cooperation with provincial/municipal fisheries offices is implementing a number of initiatives to crackdown on illegal fishing activities and to raise awareness of fisheries protection resources.

  • On community fisheries, regulations to execute and further extend the Royal Decree and Sub Decree have been prepared.  On Marine conservation, the 10-year-Action Plan of Coral Reef and Sea Grass Management has been finalized.

73.     With respect to the fifth JMI in this area,          

  • In collaboration with Provincial Agriculture Departments the DoF is taking measures to suppress cutting flooded forest activities. It is cooperating with lot operators to help in protecting illegal fishing during closing season.

  • There are still difficulties in getting information on developments in forest areas from different agencies.

4.7    Private Sector Development

74.    At the 7th CG Meeting, the following JMIs were agreed in this area:

  1. The Government will establish a single entry point, or Single Window, that will allow parties involved in trade to fulfill the documentary requirements for import or export in a single transaction. Multiple interactions with agencies will be replaced by information sharing within Government.  This will be achieved as a key step toward an automated Single Window process including CED and other relevant agencies.

  2. The revised PPI process articulated in the draft Law on Concessions will be adopted by the Council of Ministers and submitted to the National Assembly during 2005.   Implementing Regulations will be issued by June 2005. Beginning June 2005, any new PPI deals will be done in conformity with the law as submitted to the National Assembly and the implementing regulations.

  3. The Council of Ministers will approve an SME development framework, including a definition of SMEs to be used among all Government agencies, developed by the SME committee and in coordination and consultation with other line ministries and private sector representatives.

  4. The draft Law on Commercial Arbitration is adopted by the Council of Ministers and submitted to the National Assembly.  As evidence that the law is implemented, at least one recognized arbitration center, with appropriately trained and respected staff and a roster of trained and respected arbitrators will have issued at least two arbitration judgments.

75.     Significant progress has been made on all JMIs in this area. For the Royal Government the private sector is the engine of growth. The Royal government's policy with respect to fostering private sector development is to play a strategic role in creating an enabling environment for the development of private enterprise, and to manage the development process. As further support to the Government-Private Sector Forum mechanism on policy guidelines a Private Sector Development Steering Committee was established in July 2004 that is Chaired by the Senior Minister and Minister of Economy and Finance. Under the Steering Committee, three Sub Steering Committees have been established: one dealing with Investment Climate and Private Participation in Infrastructure (PPI) that is chaired by Senior Minister, Minister of Economy and Finance, second on Trade Facilitation that is chaired by Senior Minister and Minister of Commerce, and third on SME's that is chaired by the Minister of Industry, Energy and Mines. In the area of trade facilitation, a strategy on administrative document, single window and risk management is currently being prepared and will be finalized in 2006.

76.   Following the recommendations of the 8th Government-Private Sector Forum, the Ministry of Economy and Finance issued Prakas Number 298, dated 17 June 2005, on the implementation of VAT for supporting industry or subcontractors who are supplying goods or services for garment export, textile, and shoe industries. As provided in this Prakas, for supporting industry, the duty on inputs for the calculation of VAT on the import of production inputs and equipment used for direct supplies to the garments, textile and the shoe industries should be born by the Government. The VAT on products and services used for exports is at the zero percent rate.

77.    As for the enterprises under the real regime of taxation, supplying directly 80 percent of its production or services to exporters of the garments, textiles and shoe industries, the VAT on their production outputs is at a zero percent rate.

78.    Investment related regulations have been promulgated i.e. the Sub Decree on the implementation of  the Amendment to the law on Investment, the Sub Decree on the establishment of provincial-municipal investment Sub Committees, and the Sub Decree on the establishment and management of Special Economic Zones.

79.   The RGC has also developed other key legal infrastructure to sustain the development of the financial sector such as the Law on Commercial Enterprises. This Law can be implemented without Sub-Decree. The Draft Law on Government Securities, the Draft Law on Issuance and Trading of Public Securities, and the Draft Law on Bankruptcy will soon be submitted to the Cabinet. The Draft Law on Secured Transactions has been already adopted by the Cabinet. Meanwhile, the Ministry of Economy and Finance and the National Bank of Cambodia are preparing the Draft Law on Leasing.

80.   With respect to the first JMI, "establish a single entry point, or Single Window” due to the complexity and cross cutting nature of the task, more time will be needed before the implementation of the Single Administrative Document (SAD), the Single Widow and the Risk Management Strategy. It is expected that the aforementioned activities will take place in 2006.

81.   The Trade Facilitation & Competitiveness Project initiated by the Royal Government of Cambodia in 2005, incorporates a number of components which collectively define a broad range of reforms to be implemented. These reforms, which impact and require the support of a number of government agencies, will affect numerous stakeholders within the private sector and government. However, pre-dating the current project, several changes have already been instigated, in particular since the Investment Climate Assessment study conducted for Cambodia in 2003.

82.   The results of the Reform Score Card survey undertaken by Emerging Markets Consulting show that government agencies have made strong improvements in the eyes of the private sector in terms of, among others, costs, time and information dissemination:

83.   There has been a sharp drop in the number of firms reporting problems with their documentation during the importing and exporting process. In 2003, roughly 49 percent of firms reported encountering problems that has significantly declined to only 13 percent of firms who have recently reported encountering difficulties. The average costs have also decreased from $2,477 per import transaction in 2003 to about $673 per transaction in 2005, and for exports, from $942 in 2003 to $598 per transaction in 2005. The private sector perception of the amount of time required to process transactions has also improved, with respondents reporting a reduction in processing time of over 20 percent from 2003. Concerning government’s dissemination of information – an important capability assessed via the survey – 84 percent and 91 percent of respondents said they were at least adequately informed about fees and documentation respectively.

84.   With respect to the second JMI, the Law on Concessions was adopted by the Cabinet on July 15, 2005.

85.   With respect to the third JMI, the SME development framework was adopted by the Cabinet on July 29, 2005. The activities in the action plan to implement the SME Development framework are now aimed at streamlining and simplifying administrative procedures for SME registration and operations.

86.   With respect to the fourth JMI concerning the Law on Commercial Arbitration, the draft Law is now being reviewed by the Commission No. 9 of the National Assembly.

4.8   Gender, Poverty and HIV/AIDS

87.   At the 7th CG Meeting, the following JMIs were agreed in this area:

  1. These will be treated as cross cutting issues to be addressed under the broader umbrella of formulating the next 5 year National Strategic Development Plan for 2006-2010.

  2. Gender Equality: Put in place the Legal Framework for Protection

  • Draft Domestic Violence Law is adopted by the Council of Ministers and submitted to the National Assembly and a Prevention Plan adopted

  • Draft Anti Trafficking Law is adopted by the Council of Ministers and submitted to the National Assembly  and a Prevention Plan adopted

88.   With respect to the first JMI in this area related to addressing the cross-cutting issues in the formulation of the National Strategic Plan (NSDP) 2006-2010, the concerned TWGs have reported that the NSDP that has been formulated by the Royal Government in close consultations with all development partners and civil society representatives is more responsive to cross-cutting issues than any of the previous Socio-economic Development Plans.

89.    The Royal Government is pleased to report that significant progress has been made on the second JMIs in this area. The "Law on Prevention of Domestic Violence and Protection of the Victims" was promulgated on 5 November 2005. A Sub-decree is being drafted and a prevention plan is being developed. The "Law against Trafficking in Person and Sexual Exploitation" is being reviewed by the Ministry of Justice in close consultation with the Ministry of Women Affairs. Also, the UN protocol on Prevention, Intervention and Punishment of Human Trafficking was ratified by National Assembly on 25 November 2005.

4.9    Health and Education

90.    At the 7th CG Meeting, the following JMI was agreed in this area:

  • Timely disbursements of the budget for Health and Education as agreed in the  PFM Action Plan.

91.    In 2005, total disbursements of the budget to the Ministry of Health were as follows:

  • At the Central Level, total disbursements (147.7 billion CRs) amounted to 92 percent of planned budget allocation (160.3 billion CRs), and 95.5 percent of the amount requested (153.6 billion CRs) by the MOH against planned budget allocation. The PAP disbursements (30.1 billion CRs) were 81.3 percent of planned budget allocation (37.0 billion CRs) and 83.5 percent of the amount requested by MOH.

  • At the Provincial Level, total disbursements (51.0 billion CRs) amounted to 65 percent of planned budget allocation (78.5 billion CRs). The PAP disbursements (11.7 billion CRs) were 60.3 percent of planned budget allocation (19.4 billion CRs).

92.   In its report to the GDCC, the Ministry of Health has noted that the reason for delays in disbursements to provinces is the weak budget management capacity at MOH, especially at the provincial level, and the complexities of disbursement process at the central-provincial level. The Royal Government urges the development partners working with the MOH to give a priority to strengthening the MOH's budget management capacity at both the central and provincial levels.

93.   In the case of the Ministry of Education, the overall budget for PAP 2005 of the Ministry of Education, Youth and Sports was 86.7 billion Riels. As of 25 January, 2006, some 70.3 percent or 61 billion CRs were disbursed. These included:   

  • At the central level, disbursement of 13.3 billion CRs or 37.3 percent of the PAP budget allocation for the central (35.7 billion CRs).

  • At the Provincial level, disbursement of 47.7 billion CRs or 93.5 percent of the budget allocation for the provincial level (51 billion CRs).

94.   The Ministry of Education, Youth and Sports has reported to the GDCC several reasons for delays in disbursements of PAP budget allocations. These include: late submission of requests, need to improve submission process, need to follow MEF procedures consistently, and delays in the utilization of PAP budget for the year until the start of the school year i.e. the month of October. The need for more negotiations with MoEF to improve cash flows systems by reducing the number of disbursement tranches is also identified. The MoEYS's priority is to strengthen its budget planning and management capacity at both the central and provincial levels. The Royal Government urges the development partners working with the MOEYS to give a priority to strengthening its budget planning and management capacity at both the central and provincial levels.

4.10     Harmonization and Alignment

95.    At the 7th CG Meeting, the following JMI was agreed in this area:

  • Implement--and monitor implementation progress on a six monthly basis—the Harmonization Action Plan and the Partnership Principles

96.    The Royal Government is pleased to report that the JMI in this area has been met. Cambodia's Report on "Progress Toward Enhanced Aid Effectiveness" was presented by H.E. Senior Minister Keat Chhon, Minister of Economy and Finance, and the First Vice Chairman of the Council for the Development of Cambodia at the Second High Level Forum held in Paris on 28 February - 2 March 2005, at the close of which the Paris Declaration was issued. The six month progress report was presented and discussed with development partners at the Partnership and Harmonization TWG meeting on 4 July 2005 at the Council for the Development of Cambodia. More details on recent developments in this area and the progress made in 2005 are presented in Chapter IV.
 

| Content | Back | Top | Next |


Home | 8th CG Meeting | 7th CG Meeting | Partnership and Harmonization TWG | GDCC | Policy Documents Guidelines | Donor Dev. Coop. Pgm. | NGO