This quarterly progress report from each Joint Technical Working Group is requested by the Secretariat of the Government-Donor Coordination Committee (GDCC) before 25 February 2005. It will be used to prepare a briefing note for the Second GDCC Meeting scheduled to be held on 7 March 2005. Please return the completed questionnaire to H.E. Chhieng Yanara at CDC in both soft and hard copy.
TECHNICAL WORKING
GROUP (TWG):
Gender |
If Yes: When was the Action Plan approved by the TWG? (date / month / year) 11/11/2004
If
No, please go to Q8, but first please identify the methodology that is
planned to be employed by the TWG to monitor and report on progress made:
............................................................................................. |
|
|
|
|
Activity (please use the same number as shown in Q5) |
Comments, if any |
i.
Audit is complete First draft of Government /Donor strategy drafted MOP called first meetings on NSDP on 14 Feb & 28 Feb |
|
ii. Annual workshop on gender mainstreaming in Seila Program 2004. Gender training for Provincial Investment Plans for all provinces. Began development of guidelines for gender mainstreaming in Commune Investment Plans | |
iii. Inter ministerial consultations completed in Council of Ministers. Prime Minister has requested Parliament to make consideration of DV Law a priority of the Parliament | |
iv. Amendment of Anti Trafficking Law complete and defense is continuing in Inter Ministerial Committee of Council of Ministers | |
v. Social Work Institute has begun training of counsellors and social workers for victims of violence | |
vi.
Maternal mortality |
Report needed from MOH |
xi.
Negotiations with donors to build dormitories are progressing |
|
|
||
Activity |
Reasons for Delay | TWG's Recommendation |
Please use an extra sheet if you need more space. |
|
|
|
Activity |
Comments, if any |
Please use an extra sheet if you need more space. |
|
If Yes, please list the indicators below:
|
|
|
|||
Joint Monitoring Indicator | Progress | Constraints | Recommendation |
i. Passing of Domestic Violence Law and adoption of Prevention Action Plan |
Currently being considered by Inter Ministerial Committee of Council of Ministers | ||
ii Passing of the Anti
Trafficking Law and adoption of Prevention Action Plan
|
None
|
Other priorities of the COM | Ministry of Justice and Ministry of Women’s Affairs requested by TWGG to follow up |
|
|
|