Scheduled Activities |
Implementation Status |
On Schedule |
Behind Schedule |
If behind schedule, reasons for delay |
TWG Recommendations for GDCC Consideration, if any |
Monitor Sector Performance |
Progress of Sector 2005-2006 MTR
-
Set up
of MTR (discussion and agreement on MTR for HSP)
-
Presentation of cover framework, TOR, roadmap to implementation,
studies, MTR report
|
X: Framework and roadmap for MTR reviewed and agreed. TORs for
specific inputs to MTR developed; procurement for TA to support
MOH and partners under way |
|
|
|
i
Progress of AOP 2006’s implementation
Joint Annual Performance Review
Quarterly update at TWGH meeting |
X: JAPR March 15-17 |
|
|
|
Budget Disbursement (JMI)
|
X: Disbursement 2005 and for 1st quarter 2006 reviewed |
|
|
|
Progress of Health Sector Support Project
|
X: Progress update HSSP April 2006
Monthly update on MTR preparation process |
|
|
|
Progress of National Program
Monthly presentation at TWGH meeting |
X: Malaria & Dengue, National Immunization Program, Nutrition |
|
|
|
Principal Recipient for GFATM
Semi-annual presentation at TWGH meeting |
X: Update April 2006 |
|
|
|
Regular inputs from Civil Society
|
X: NGO representative member of the TWGH and Secretariat. Present
in HP meetings |
|
|
|
Sector Harmonization and Alignment |
Facilitate salary supplement phasing out and
Performance Based Incentive Reform
-
Briefing at TWGH meeting in February to prepare for CG meeting
in early March
-
Progress in MoH High Level Group & Health Partner WG work to be
monitored.
-
Follow
up of salary incentive scheme & timeframe development for
implementing incentive schemes
-
Follow
up of PMG in consultation with CAR
CAR, MEF and HP to
be engaged by MoH to discuss on revised incentives (incl.
sequencing) |
X: Progress reported.
Tripartite Working Group MoH-CAR-HP established: 2 meetings held;
2 day joint field visit to “contracting” ODs;
MOH HLWG has met regularly;
HPs have provided feed back to the MOH on MBPI proposals;
|
|
|
|
SWiM development toward SWAp |
X: SWiM review to be carried out as part of MTR; TOR prepared |
|
|
|
Refine role, structure and function of Pro-TWGH
Quarterly report of progress and feedback from TWGH secretariat |
X |
|
|
|
Refine role, structure and functions of Sub-TWGH |
X: Sub-Cocoms Assessment was carried out followed by
identification of 9 Sub-TWGHs to function with revised TOR and
membership |
|
|
|
Strengthen capacity building of TWGHS
|
X: Options
for capacity building to be discussed during June secretariat
meeting. |
|
|
|
Key Strategic Issues |
Health Service Delivery |
Contracting Follow up |
X: Contracting review part of MTR; ToR prepared; call for
Expressions of Interest published |
|
|
|
Consumer and Provider rights |
X |
|
|
|
Review linkages of Child Survival, Reproductive
Health and HIV/AIDS |
X:
Sexual and Reproductive Health Strategy incorporates linkages RH-HIV
and RH-CS.
Child Survival Strategy distributed |
|
|
|
Health Financing:
User-fees and access
Report on Field Assessment for implementation of officially
approved user-fees |
X: Access study phase I distributed |
|
|
|
Budget Disbursement
Linking planning, allocation, budgeting and
budget execution incl. follow up work on PETS
-
Health PETS reports
-
Program-Budgeting Framework
-
TAG to prepare recommendation on Budget
Disbursement for JAPR 2006
|
X: Programme Based Planning implemented for Annual Operational
Plan 2007.
Budget Disbursement Rate Q1:
Central level: 31%
Provincial level: 2% |
TAG recommendation |
Decision taken to defer TAG budget disbursement recommendation
pending outcome Health PETS |
|
Human Resources
Comprehensive midwifery review |
X: ToR and preparatory activities carried out and review will
start in June/July 2006 |
|
|
|
Private sector
Health Professional Registration |
X |
|
|
|
Preparedness planning for pandemic influenza |
X: AI and PI preparedness plan for health updated as part of the
Cambodia Comprehensive Avian and Human Influenza Plan |
|
|
|