Six Month Progress Report of the Joint
Technical Working Groups
For the Period: December 2005 - May 2006
This questionnaire on progress made by each Joint Technical Working
Group is requested by the Secretariat of the Government-Donor
Coordination Committee (GDCC). It should be completed and submitted to
the Secretariat of the GDCC before
29 May 2006.
It will be used to prepare a summary progress report for the seventh
GDCC Meeting scheduled to be held on 14 June 2006. Please return the
completed questionnaire to H.E. Mr. Chhieng Yanara at CDC/CRDB in both
soft and hard copies.
TWG: Public Financial Management
A. Progress in Implementing TWG's Action Plans
-
Please list
below activities in the Action Plans that were scheduled to be
implemented during the last six months (December 2005 to May 2006) and
provide an update on implementation
status of these
activities.
Scheduled
Activities |
Implementation Status |
On Schedule |
Behind
Schedule |
If behind
schedule, reasons for delay |
TWG
Recommendations for GDCC Consideration, if any |
There are 254
actions planed for the implementation. |
217 (85%) |
37 (15%) |
There are
four main reasons for the delay:
1.
It
is taking longer than expected to coordinate with MEF departments
and between MEF and relevant institutions.
2.
Certain activities are pending completion of pre-requisite
activities.
3.
Procurement for services has taken longer time than planed (e.g.
in selection of appropriate consultants).
4.
Requirement to meet emerging needs for additional technical
assistance within the context of a capacity development strategy.
|
1. To further improve coordination both within MEF’s departments
and with related institutions, and decision making process.
2. To finalize TA coordination and recruitment strategy.
3. To develop fast track procurement of goods and services in
priority activities.
4. To finalize the action plan and time frame of the priority
areas (capacity development, streamlining of payment process,
revenue forecasting, budget integration, cash management and MBPI
administration) need to be completed for the Platform 1, as agreed
during the annual review.
|
-
Are there any other
issues affecting the implementation of TWG Action Plan that it would
like to submit for GDCC's consideration.
Enhanced
coordination among donors, TA providers and Government related to Public
Financial Management reforms.
Five key areas related to this are as follows: i) Need to ensure that
PFM related reforms being considered and/or implemented in line
ministries be endorsed by MEF. This is to ensure that the PFMRP is not
compromised. Ii) Need to ensure that PFM proposals from Donors that
conflict with current Government policy and /or commitments be addressed
in the first instance in the DPC and then in the TWG. iii) Need to
ensure that work of in-country TA are coordinated in way that ensures
the delivery of consistent and non-conflicting advice.
B. Progress on Joint Monitoring Indicators
-
If there
are any Joint Monitoring Indicator(s) agreed at the 8th CG
Meeting held in March 2006 that fall within the mandate of this
TWG, please list the JMIs below and indicate progress that has been
made toward achieving the JMI targets.
Joint
Monitoring Indicator |
What is the
current implementation status? What are the constraints that you
are experiencing, if any? What recommendations do you have, for
GDCC consideration to resolve the identified constraints? |
Continue
implementing the RGC's PFM Reform Program (complete
Stage1/Platform 1 and begin implementing the action plan for Stage
2) and monitor impact through the agreed PFM Performance
Management Framework/Indicators. |
_The draft of
action plan to complete Stage 1/ Platform 1 and for stage 2 were
done and are going to be finalized and implemented until the end
of 2006.
_Following
the Annual Review retreat of the PFMRP, revised PFM PI’s for 2006
have been drafted. MEF consultation internally and with
development partners is ongoing. Discussion with key stakeholders
on PI Indicator # 4, related to PFM related indictors for MoH and
MoEYS, has commenced.
_Revising
Consolidated Action Plan (CAP) and developing strategic plan for
completing Platform 1 and preparing action plan for Platform 2.
|
C. Implementation Status of the Action Plan on
Harmonization, Alignment and Results
-
What
actions have you taken to implement the updated Harmonization,
Alignment, and Results Action Plan?
What are the
constraints that you are experiencing, if any?
What recommendations
do you have, for GDCC consideration to resolve the identified
constraints?
Action Taken |
Update |
i. Building
on established donor coordination arrangements between donors,
government and TA providers. |
Coordination
committees generally functioning well. There remains some room for
improvement in donor and TA coordination related to FMIS issues.
|
ii.
Progressed fund pooling arrangements under the PFMRP though the
MDTF and the future PFMAP- IDA grant. |
SWAp like
arrangements established to allow pooling of funds under one
special account. |
iii. All
performance results targets used by development partners are
founded on PFMRP performance monitoring framework |
Poverty
Reduction Support Operation (PRSO), MDTF, and Public Financial
Management and Accountability Project (PFMAP) Indictors aligned
with PFMRP, |
IV.
Harmonized procurement and financial management manuals |
Training on
manual/s delivered |
V.
Harmonization of and integration of donor project reporting and
administration. |
Building on
work of CDC, Department of Investment and Cooperation (DIC) is
mobilizing TA to support development of systems to develop and
automate a harmonized approach to donor project reporting and
administration. |
D. Resource Mobilization
-
Has the TWG
been able to mobilize the resources to implement its Action Plan for
2006?
R
yes £
no
MEF and the WB
successfully negotiated a Public Financial Management and Accountability
Project (PFMAP) for $ 14 million.
If no, please answer the following questions:
-
What is the
total amount of resources the TWG had estimated to implement its
Action Plan for 2006? (in USD).................
-
What is the
minimum additional amount that the TWG needs to implement its Action
Plan? (in USD)...................................
-
Which
development partners do you think would be able to provide the
required resources?...................................................
Report endorsed by:
TWG Chair(s): ________
____________ _______ Lead Donor
Coordinator(s): _________ ___________ _______
Name Signature
Date Name
Signature Date |