Six Month Progress Report of the Joint
Technical Working Groups
For the Period: December 2005 - May 2006
This questionnaire on progress made by each Joint Technical Working
Group is requested by the Secretariat of the Government-Donor
Coordination Committee (GDCC). It should be completed and submitted to
the Secretariat of the GDCC before
29 May 2006.
It will be used to prepare a summary progress report for the seventh
GDCC Meeting scheduled to be held on 14 June 2006. Please return the
completed questionnaire to H.E. Mr. Chhieng Yanara at CDC/CRDB in both
soft and hard copies.
TWG: PUBLIC ADMINISTRATION REFORM
A. Progress in Implementing TWG's Action Plans
-
Please list
below activities in the Action Plans that were scheduled to be
implemented during the last six months (December 2005 to May 2006) and
provide an update on implementation
status of these
activities.
Scheduled
Activities
|
Implementation Status |
On Schedule |
Behind
Schedule |
If behind
schedule, reasons for delay/notes for CDC information |
TWG
Recommendations for GDCC Consideration, if any |
1.
Disseminate new strategy on phasing out salary supplementation |
X |
|
|
|
2. Complete
information gathering on salary supplementation |
|
X |
Some donor
responses were delayed. Now CAR
will prepare a report on the responses and write to TWGs on action
planning stage. |
|
3.
Remuneration study |
|
X |
Timing was
for completion in July, but study now is to be finished in August |
|
4. Employment
Study |
|
X |
Timing was
for completion in July, but study now is to be finished in August |
|
5. HRM Policy
Outline |
X |
|
|
|
6.
HRM Guide
|
X |
|
|
|
6.
One Window Office Legal Status |
X |
|
|
|
7. HRD
Policy Outline |
X |
|
|
|
8. HRD Master
Plan |
X |
|
|
|
|
|
|
|
|
-
Are there
any other issues affecting the implementation of TWG Action Plan that
it would like to submit for GDCC's consideration.
No. The PAR TWG members
recognize that the work required under the Joint Action Plan for 2006 is
demanding and that there needs to be further discussion on the capacity
and resources needed to meet all the priorities in the remaining time
available. The PAR TWG members will work together to ensure there is a
realistic plan for addressing these issues.
There is an ongoing
systemic problem in resourcing PAR in an adequate, timely and
predictable way. The TWG has yet to develop a solution.
B. Progress on Joint Monitoring Indicators
-
If there
are any Joint Monitoring Indicator(s) agreed at the 8th CG
Meeting held in March 2006 that fall within the mandate of this
TWG, please list the JMIs below and indicate progress that has been
made toward achieving the JMI targets.
-
Joint
Monitoring Indicator |
What is the
current implementation status? What are the constraints that you
are experiencing, if any? What recommendations do you have, for
GDCC consideration to resolve the identified constraints? |
1. Implement the approved "Joint
Government-Donor Strategy for Phasing Out Salary Supplementation
Practices in Cambodia" by: (a) implementing approved sectoral
action plans; and (b) establishing Priority Mission Groups (PMGs),
and PMG/Merit Based Pay Initiatives (PMG/MBPIs) in MEF, MOH, and
at least one other ministry/agency. |
Responses to
information questionnaire have been received from some but not all
donors, despite follow up. Danida has recently agreed to resource
data entry in relation to the response that have been made. The
slow response rate has delayed action planning, which is now
underway in Education, Health and PAR sectors but needs to proceed
more generally. MBPI proposal for Health has been developed but
has yet to be submitted to CAR. Other possible MBPI proposals
are at early stages in consideration in five other Ministries
|
2. Improve pay and employment
conditions in the civil service by developing and implementing:
(a) a medium term strategy and action plan to enhance
remuneration; and (b) a redeployment policy and action plan. |
Two studies
on remuneration and employment issues are to be conducted over the
next two months before the policy development work is undertaken.
|
3. Design and implement an HRM
policy and action plan to improve merit and performance management
by introducing an HRM Guide and further developing the Human
Resource Management Information System (HRMIS) for the Civil
Service. |
The draft HRM
Policy Outline and HRM Guide have been developed. Resources are
being negotiated for further policy development work through
AusAID. However, implementation of these new arrangements, planned
for later in the year, has yet to be resourced |
4. Enhance service delivery though
developing a One Window Offices (OWOs) policy, legal framework and
implementation plan, including establishment of at least 5 OWOs
across Cambodia |
A draft
Anukret on One Window Offices has been prepared and extensively
consulted on within Government. Implementation of planned One
Window Offices later this year has yet to be fully resourced. |
C. Implementation Status of the Action Plan on
Harmonization, Alignment and Results
-
What
actions have you taken to implement the updated Harmonization,
Alignment, and Results Action Plan?
What are the
constraints that you are experiencing, if any?
What recommendations
do you have, for GDCC consideration to resolve the identified
constraints?
Action Taken
|
Update |
i.Within the
framework of NSDP, sector ministries and agencies develop sector
plans and prioritized results based programs, and a sector MTEF. |
National
Public Administration Reform Plan in place. Governance Action Plan
No 2 recently agreed by Government. CAR Work Plan also in place. |
ii All sector
plans and development programs/projects include an assessment of
the existing capacity gaps and a capacity development plan to fill
the gaps to achieve targeted development results. |
CAR Capacity
Plan developed and being implemented, with support from CIDA. |
vi Concerned
TWGs develop an implement an action plan to strengthen the
technical and policy capacity of relevant institutions to carry
out environmental analysis and to enforce legislation. |
This is part
of the CAR Capacity Plan. |
D. Resource Mobilization
-
Has the TWG
been able to mobilize the resources to implement its Action Plan for
2006?
£
Yes R
No
(See comment under 2 above)
Report endorsed by:
|