TWG: PUBLIC FINANCIAL MANAGEMENT REFORM PROGRAM

A.    Progress in Implementing TWG's Action Plans

  1. Please list below activities in the TWG Action Plans for 2007 and 2008 that were scheduled to be implemented during the period October 2007 to February 2008 and provide an update on implementation status of these activities.

Scheduled Activities

Implementation Status

On Schedule

Behind Schedule

If behind schedule, reasons for delay

TWG Recommendations for GDCC consideration, if any

  1. Continue implementing key remaining action plan necessary to complete platform one:

  1. Continue improve cash management

  2. Continue improve debt management

  3. Continue streamlining budget execution procedure in line with FMIS.

  4. Continue improve budget comprehensiveness and integration.

  5. Continue improve revenue policy and forecasting.

a, b on schedule

c, d, e behind schedule

These activities need longer time for implementation.

These activities will be continued in Stage 2/Platform 2

  1. Preparing Consolidated Action Plan for Stage 2 (CAP2):

  1. Platform 1 activities to be strengthened in stage 2

  2. Platform 2 activities to be implemented in stage 2

  3. Later platforms to be commenced now.

On schedule

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  1. Are there any other issues affecting the implementation of TWG Action Plan that it would like to submit for GDCC's consideration?

B.    Progress on Joint Monitoring Indicators

  1. If there are any Joint Monitoring Indicator(s) agreed at the 1st CDCF in June 2007 that fall within the mandate of this TWG, please list the JMIs below and indicate progress that has been made toward achieving the JMI targets. Please take care to indicate if resource needs or appropriate timeframes still need to be identified.

Joint Monitoring Indicator

 

Timeframe

What is the current implementation status?

What are the constraints that you are experiencing, if any?

What recommendations do you have, for GDCC consideration to resolve the identified constraints?

Continue implementing the PFMRP (by sustaining actions already
implemented, by completing the remaining key actions necessary for Platform 1,and by preparing the consolidated action plan for implementation of Stage
2/Platform 2) and continue monitoring impact through the agreed PFM Performance
Indicators.

Platform 1/ stage 1 completed by December 2007

Platform 2/Stage 2 Consolidated Action Plan has been prepared.

 

On schedule

 

 

 

 

 

 

 

 

 

 

 

 

 

 

C.    Implementation Status of the Action Plan on Harmonization, Alignment and Results

  1. What are the main actions have you taken to implement the Harmonization, Alignment, and Results Action Plan? What are the constraints that you are experiencing, if any?

What recommendations do you have, for GDCC consideration to resolve any identified constraints?

Relevant section and sub-section of the H-A-R Action Plan

 

Action Taken

 

Constraints and/or recommendations for GDCC discussion

Ownership

PFMRP – Consolidated Action Plan for Stage 2 in Place.
PFMRP MDTF and Co Financing IDA Grant in Place
MEF PFM Reform Committee leads Reform Programme Implementation

Work ongoing to incorporate NAA into mini swap.

Alignment

PFMRP represents coordinated assistance by the DP to RGC PFM programme
PFM Assessment methodology built into programme indicator set.
Annual Retreat and external reviews
Majority of aid untied some small scale bilateral components

 

Harmonization

Full PFM Swap

 

D.  Resource Mobilization

  1. Please provide details of your TWG's resource mobilisation efforts since the June 2007 CDCF meeting (including identified resource needs, actual commitments and source of funds, and remaining gaps) and the extent to which these resource mobilisation efforts are linked to an Action Plan or sector programme that includes a budget framework for programming resources and activities within the domain of the TWG On going Program

  1. Does the TWG have sufficient resources to manage the workload identified in its Annual Workplan?    Yes

  1. Has your TWG submitted a request for support to CDC/CRDB ?                             No  

  1. If "No", is your TWG considering a request for support?                                       No

 