ANNEX 1
DEVELOPMENT COOPERATION PROGRAM MANAGEMENT CYCLE
Development assistance programming is undertaken in the context of the
program and project cycle management. The project cycle refers to the
steps or stages that a project undergoes from the time it is only an
idea until the time it is completed. The cycle is applicable to donor
support as well as for the formulation of the donor country strategy and
country program which provides the macro-perspective for donor
assistance programming. An overview of the program/project cycle is
presented in Figure 1 below.
FIGURE
1: PROGRAM/PROJECT MANAGEMENT CYCLE
The central role of
country strategy indicates the overarching strategic framework within
which a portfolio of projects funded by a donor is developed. The stages
in the project cycle are:
1. Project
identification. |
4. Project implementation. |
2. Project
formulation. |
5. Project
monitoring and evaluation. |
3. Project appraisal and
approval. |
6. Project completion and
follow-up. |
Throughout the entire
project cycle lessons learned and best practices are assimilated to
refine and enrich the project design and implementation strategies.
Successful experiences are scaled up, to inform policy debate and enable
replication for wider coverage and scale.
ANNEX
2
KEY ISSUES AND AREAS TO BE COVERED IN A PROJECT DOCUMENT
The preparation of a
project document should cover the following issues and requirements that
must reflect the design of a development intervention.
-
Context and
situation analysis
-
Capacity development
requirement and assessment
-
Strategy and
objective of donor support
-
Project description:
- |
Project
strategy |
- |
Outcome
and partnership strategy |
- |
Outputs
and activities |
- |
Inputs |
- |
Sustainability,
risks and prior obligations |
- |
Management
arrangements |
- |
Monitoring,
review and evaluation with learning |
- |
Reporting |
-
Work plan
-
Budget
-
Annexes, such as:
- |
Legal
instruments for execution and implementation arrangements |
- |
Terms
of reference of key consultants and experts |
- |
Strategy
and scope of training |
- |
Equipment
specification |
CONTEXT AND SITUATIONAL ANALYSIS
This part of the project document should provide an analysis of the
development problem being addressed. The content is based on the
information gathered during the problem definition stage using the log
frame, results analysis and other baseline studies. It should include:
-
The contextual
issues of the national development problems that are being addressed
in the project intervention.
-
Baseline information
and measurable indicators of the problems that can be used to
demonstrate that the proposed development intervention would
solve/address the problems.
-
The population or
target groups affected; and gender and environmental aspects of the
problem.
-
Previous experiences
and lessons learned from efforts of national and international
partners.
-
The national program
context of the project interventions should be briefly described.
Alternatively, an implicit national program may exist and this may
be identified through an analysis of government plans and policy and
strategy statements. The description of the national program should
cover objectives and strategies of the Government; structure and
components; efforts currently being made by the Government and
national institutions as well as international development agencies
in support of the national program; institutional arrangements for
the management of the program, including inter-ministerial
coordinating arrangements, legislative requirements, etc; and
resources allocated and expected. The Government may find the
project intervention as providing an opportunity to develop a
comprehensive national program.
CAPACITY DEVELOPMENT REQUIREMENT AND ASSESSMENT
Capacity development should be an overriding objective of development
assistance. Project formulation exercise must therefore identify and
analyse the capacity development issues and requirements as part of the
solutions being proposed. Important aspects of capacity requirements are
strategy and policy formulation, legislation, human resources,
technology, management capacities, monitoring and evaluation capacities,
learning and knowledge integration capacity, aid coordination and
resource mobilisation. The project document should outline the precise
areas of capacity that must be addressed for the successful
implementation of the project intervention.
The present situation in Cambodia would warrant special attention to the
following capacity building inputs:
-
Maximise utilisation
of national experts. The Government-Donor TWG mechanism
should be used to harmonise the “pricing” structure and terms and
conditions of employment of national consultants/experts. These
measures may also have to be placed in the context of developing
capacity of the “knowledge industry” in Cambodia.
-
If monetary
incentives must be given to counterpart staff their application
must be done in a transparent and coordinated manner through
consultation between donors and the Government. Government and
donors must cooperate on arriving at a coordinated strategy of
eliminating the incentive schemes in the context of sustainability
of donor supported development interventions.
-
Training
activities should be coordinated at the sector program or line ministry
level. Ministries/departments should be encouraged to develop their
respective competency plans in relation to their respective sector or
cross-sectoral development programs. At the sector line ministry level,
a database of training and some form of “skills registry” system should
be maintained to track competency building activities and their
effective application in the organisational system.
STRATEGY AND OBJECTIVE OF DONOR SUPPORT
This section should provide an explanation for donor support to the
national program. It should offer a description of how the project
support is consistent with the donor’s country strategy for Cambodia;
the strategic advantages the donor possesses; and how the donor’s
resources will be allocated to achieve the solution to the problem.
PROJECT DESCRIPTION
The core design of the project intervention should be presented in this
section. Using a result-based approach to project intervention, the
project description should cover the following areas:
-
Project
strategy. The project strategy that should address:
-
project
intervention approach and methodology,
-
specification of
innovative models and concepts,
-
strategies and
institutional mechanisms for up-scaling the models being pursued
for validation under the project,
-
implementation
arrangements including identification of roles and
responsibilities of the institutions and partners,
-
aid coordination
arrangements in the case of multiple donors involved in the
project, and
-
exit strategy of
the donors and sustainability of the development intervention.
Host national
institutions must ensure that new concepts and models pursued
through donor-assisted projects are subject to coordination at the
sector or program level. The objective is to have mechanisms in
place for monitoring and learning and eventually up-scaling
successful pilots. Care should be taken to prevent proliferation of
pilot schemes that may exert considerable management burden on
national institutions and result in misallocation of resources.
-
Outcome and
partnership strategy. The development outcome to be achieved
through the donor support. The time frame and measurable indicators
for the achievement of the outcomes/effects should be stated. The
partnership strategy should specify other Government agencies,
bilateral and multilateral donors, NGOs, as well as private sector
implementing partners whose involvement is critical to the
successful outcome of the project intervention.
-
The Outputs
of the project must be defined in measurable terms and organised
according to the attainment of an outcome or effect of the project
intervention. Indicators and time frame of attainment of each output
must be stated to enable monitoring progress toward producing output.
-
Activities
that must be carried out in order to produce each output must be
described in substantive terms. Time frame for each activity should also
be stated.
-
Inputs are
experts/consultants, project administrative and management personnel,
volunteers, training, equipment, etc. The inputs required for carrying
out each activity should be specified.
SUSTAINABILITY, RISKS AND PRIOR OBLIGATIONS
The precise strategy and requirement for sustainability of the project
intervention must be elaborated in terms of host institution’s capacity
to sustain the effort initiated or extended through the project. Fiscal
issues, human resources provision, recurrent budgetary issues,
organisational capacity and other relevant factors that would determine
sustainability of the project intervention should be described.
Environmental risk assessment, where applicable, should also be
undertaken.
The risks that is likely to undermine sustainability and effective
implementation of the project activities should be clearly identified
and outlined as part of the project design. In this case, the
obligations of the Government and counterpart national institutions as
well as cooperation of partners should to be stated.
MANAGEMENT ARRANGEMENTS
The management arrangements should spell out the institutions – national
or international – responsible for execution or overall management of
the project. Implementing partners – national or international – are
drawn in a project to deliver the goods and services required for the
attainment of project outputs. Implementing partners should be
identified at the project design phase, however in certain cases the
identification and selection of implementing partners may have to await
commencement of project activities.
Other organisational and institutional arrangements for guiding project
implementation may also be required for the effective and successful
implementation of a project. These may include project steering
committee and project implementation committee for projects which are
not situated in the context of a SWAp.
THE OTHER ASPECTS OF PROJECT DESIGN INCLUDE:
-
Monitoring, review
and evaluation with learning
-
Reporting
-
Work plan
-
Budget – with clear
linkage between input and output required for the results framework
of a project intervention.
-
Annexes such as:
- |
Legal
instruments for execution and implementation arrangements |
- |
Terms
of reference of key consultants and experts |
- |
Strategy
and scope of training |
- |
Equipment
specification |
ANNEX
3
THE MEDIUM TERM EXPENDITURE FRAMEWORK (MTEF)
HEALTH SECTOR CAMBODIA
10
This annex provides a
sample description of the Medium Term Expenditure Framework (MTEF)
developed at the sector level. Below is a reproduction of the conceptual
framework of the MTEF for the Health Sector Strategic Plan 2003-2007.
WHAT IS AN MTEF?
An MTEF is a multi-year public expenditure plan based on sectoral
financing needs and projections for the total resource envelop available
from domestic and external resources. As information tool it serves to
program all resources and expenditure together and helps in making
resource allocation decision on priorities.
THE MTEF IN CAMBODIA
An MTEF in Cambodia is established for the first time in 2002 for the
period 2003-2007. The process is being piloted for four ministries,
health, education, rural development and agriculture and is anticipated
to integrate with the public investment program (PIP).
The intention is to enable medium term allocations for increased public
spending based on forecasts of financing needs for the social sector. In
this regard, each line ministry is required to provide indicative
forward projections by program area, broad line item (salary, non-salary
and capital) and sources of funds.
OBJECTIVES FOR ESTABLISHING AN MTEF
The objectives of developing an MTEF are to:
-
Fulfil government
requirements in projecting resource needs for a sector;
-
Produce a financial
plan for the priorities in a sector strategic plan;
-
Link budgetary
allocations for investment and operational costs with medium term
development plans;
-
Enable government
and partners to jointly make resource allocation decisions for
better efficiency by reducing shortfalls and duplications.
THE MAIN COMPONENTS OF THE MTEF PROCESS
Establish a fiscal framework
based on macro-economic projections and forecast revenue
collection |
Ministry of Finance |
Establish (soft) sector limits
|
Ministry of Finance, Ministry
of Health, external partners |
Develop budget estimates based
on a limited number of program categories or line items |
Ministry of Health |
Negotiation process to establish
hard sector limits based on updates on fiscal data and
relative strength of budget proposals. |
Ministry of Finance, Ministry of Health, External Partners |
RISKS AND CONSTRAINTS TO IMPLEMENTING THE MTEF
One of the most fundamental problems is the release of funds. Experience
with the MTEF process in the health sector showed that there is a
tendency for expenditure to be concentrated into the last quarter of the
year while only 1.5 percent of the budget for health was spent in the
first quarter. The situation for the first quarter of 2002 had slightly
improved but release of cash still has remained low.
Other risks to effective implementation of the MTEF are:
-
Affordability - whether the national budget projections are based on a
realistic macroeconomic framework, whether there is sufficient input
against needs from external sources and whether objectives and priority
areas are realistically defined;;
-
Accountability - whether the responsibility for developing,
implementing and monitoring plans are clearly designated among
stakeholders;
-
Transparency - the degree to how useful and clear is the budget
classification system; to what extent is non-financial program
performance measured?
-
Comprehensiveness - does the MTEF capture extra budgetary funds? Is
there consistency between national and external financing?
Many of the risks to successful implementation of the MTEF are outside
the direct control of the Ministry of Health. They rely on broader
fiscal reforms and wider attempts to reform the planning process within
the health sector. Regular releases of cash are a pre-requisite for
meeting the targets of both the MTEF plan and also non-financial targets
of achievement set by the health sector. Other constraints concern
inadequate coordination of external financing and the lack of
information regarding donor expenditures that leads to difficulty in
making strategic decisions.
ANNEX 4
PROGRAM/PROJECT PROGRESS REPORT
1. QUARTERLY PROGRESS
REPORT
The quarterly progress report (QPR) should be prepared toward the end of
the current quarter. The QPR should cover analyses of attainment of
outputs as per project document and work plan, activities undertaken to
produce the outputs, inputs mobilised and deployed, and expenditures
incurred. A summary of actual expenditure against planned budget should
be presented in the QPR; it should be accompanied by a summary estimate
of expenditure budgeted for the next quarter as well as the remainder
quarters of the current calendar year. The QPR is an instrument for the
project management to obtain advance funds.
2. ANNUAL PROGRESS REPORT
The annual progress report (APR) should be prepared at the end of each
calendar year. The APR would be considerably more analytical in content
than the QPR. It should assess the project progress or performance in
terms of both outputs and outcomes in a comprehensive manner. Lessons of
development intervention that can be learned from the project for
knowledge sharing amongst the development community and policy makers
should be documented in the APR. The APR should provide future
directions for the project (development) intervention – in terms of both
strategy and scope of development cooperation. The APR should be
accompanied by a financial report and revised budget estimates,
including projection of resource requirement for the remainder of the
project period.
The performance assessment dimension of the APR should address quality
assurance of the project. The assessment should identify critical issues
and problems of the project and offer suggestions for improvements in
project management and implementation arrangements. Projects having
serious implementation difficulties may be subject to serious
consideration for discontinuity, as per decision reached in consultation
between the relevant Government agencies, CDC and the donor(s).
The APR can be used for annual review of the sector program to which the
project has been designed to contribute to.
3. FORMAT OF THE QUARTERLY AND ANNUAL PROGRESS REPORT
In an effort to simplify reporting, the Government will work with the
Government-Donor Joint Technical Working Group to develop a standard
format for the quarterly and annual progress reports that would be used
by all agencies – government and development partners engaged in
development cooperation in Cambodia.
Below is an example of a simplified format of a standard progress report
which can be adapted for preparation of Quarterly and Annual Progress
reports.
Reporting Agency: |
[…]
|
Country: |
[…] |
No. and title: |
[…] |
Reporting period: |
[…] |
I. PURPOSE
This section includes:
-
Project intended outcomes and planned outputs.
-
Reference to how the project relates to national goals, priorities or
programs.
-
The implementing partner or contractor.
II. RESOURCES
This section includes total approved budget and summary of resources
available for the project.
III. RESULTS
Information in this section includes:
-
An assessment of progress towards the production of outcomes and
outputs planned for the year.
-
Main activities undertaken and achievements.
-
Explanation of any variation from the work plan for the year.
-
Lessons learned and knowledge gained project implementation and any
evaluations and studies that have taken place during the year.
IV. FUTURE WORK PLAN
Information in this section includes:
-
Work plan for the following year.
-
Indication of any major adjustments in the original outcomes and
outputs.
-
Estimated budget required.
V. FINANCIAL
IMPLEMENTATION
This section should include total approved project budget, current year
budget and expenditures for the year.
|